Manual Charging on TOSHIBA Injection Moulding Machines
By TOSHIBA MACHINE CO.,LTD.
MANUAL charging is necessary before carrying out the MANUAL operation, SEMI-AUTOMATIC operation and AUTOMATIC operation.
(The following descriptions are given on condition that resin has been supplied and barrel heating up has been completed before starting operation.)
Screw Rotation Speed(SRN) 20min-1
Back Pressure (BP) 49MPa (Max. setting)
* In order to avoid a problem, Back Pressure (BP) here should be high enough for the screw not to retract during its rotation.
Use the operation controller to operate the machine by following the procedure below.
[1] Press [MAN] of the OPERATION selector button.[2] Close the safety gate. Then press [INJ] of the SCREW button and move the screw to the advance limit.
[3] Continuously press [CHARGE] of the SCREW button to start charging.
※The LED blinks during charging.
※After the LED flicker became from slow to fast, charging continues without pressing [CHARGE] button.
[4] After confirming melted resin flowing out of the nozzle, increase (SRN) setting and lower (BP) setting.
※The LED lights after the completion of charging.